Used to create a choke point in the A-annulus to force the fluid flow path into the B-annulus for a more effective clean out
Impact vibration and jetting used to break up and dislodge stubborn cement or barite during washing
Hydro-Mechanical Perforator
expands to create the A B annulus cement supoprt barrier
OPERATION
The C4 annular barrier system was deployed on two wells on jointed pipe. The use of Gator Mechanical perforator allowed to gain access to the back side of the 7 in casing. The washout of the barite and cement behind the casing was completed with the Jack Hammer to place a new cement column behind the casing.
Run 1 Steps: Cut: Gator Perforating Operations
1. RIH to desired depth. Note: Wellbore fluid will by-pass through MPX
when RIH.
2. Move Gator into perforating position as per tubing tally.
3. Pressure up to specified pressure to activate MPX - shear release to
expand - set as A & B annuli plug. Gator will make its first cut
simultaneously.
4. Pressure up to specified pressure to shear the parting stem in MPX. This
disconnects the A & B annuli cement barrier (bridge plug) from the BHA.
5. Pull up to come out of the Gator Cut and move to the next position.
6. Flow at minimum specified rate to close the VCV (adjust accordingly).
7. Activate Gator perforator by pressuring up to max specified pressure or
until dump sub activates (Gator max stroke achieved)
8. Open ULS to equalize tubing to annulus by moving string into
compression.
9. Pick up and re-set Gator and repeat step #5-7 for more cuts
10. When finished cutting, POOH.
Run 2 Steps: Clean, Condition, Cement Operations
11. RIH to start position above top cuts.
12. Activate the JH by circulating at a specified rate. Continue movement
down-hole while circulating at a specified rate and rotational speed.
13. Reciprocate tubing string across perforating intervals. Repeat multiple
passes until returns are favorable (returns free of debris).
14. Stop pumping.
15. Position top diverter packer above bottom set of perfs and pump
cement spacer/conditioner bottoms up thru B annulus.
16. After specified spacer pumped away, pump cement at specified rate
while moving up-hole through the perforated interval.